Scheme Overview
Roadworks sign

-

12:00 - 23:59
Scheme Detail
Holcroft Lane, Culcheth

Residents, Businesses and Motorists are advised that major works to repair the bridge and drainage system at Aikin Knowles Bridge on Holcroft Lane are programmed to commence on 24 February 2020 and will take up to 4 weeks to complete.

The works will take place in phases, between 9:15am and 3:15pm Monday to Saturday.

The road will be fully open to traffic outside these times.

Phase 1 Starting on 24 February work will take place under temporary traffic lights for up to 2 weeks.

Phase 2 Starting on 4 April the work will continue, firstly with a road closure for 1 day, followed by temporary traffic lights for a further 2 weeks. It will also be necessary to close Holcroft Lane on Saturday 11 April. If further road closures are required these dates will be displayed on site and at www.warrington.gov.uk/roadworks.

Depending on the scope of works and traffic flows it may be necessary to use a convoy vehicle alongside the temporary traffic signals to ensure safety past these works.

Alternative Route: Glazebrook Lane, A57 Manchester Road, B5210 Woolston Grange Avenue, A574 Birchwood Way, Birchwood Park Avenue, A574 Warrington Road and vice-versa. There will be no through route from Culcheth to Glazebrook and A57 along Holcroft Lane when the road is closed.

Pedestrian access will be maintained at all times during the works.

Tan House Lane, Burtonwood

Residents, Businesses and Motorists are advised that major works to repair Tan House Lane Bridge are programmed to commence on 2 March 2020 and will take up to 12 weeks to complete.

The road over the bridge will be will be fully closed to all through traffic during these works.

Alternative Route: Burtonwood Road, Clay Lane, Chapel Lane, Farmers Lane and vice versa.

All business will be open as normal during these works.

Pedestrian access will be maintained at all times during the works.

Old Alder Lane, Burtonwood/Winwick

Residents, Businesses and Motorists are advised that major works to repair Causey West Bridge on Old Alder Lane are programmed to commence on 2 March 2020 and will take up to 12 weeks to complete.

The road over the bridge will be fully closed for the durations of the works.

Alternative Route: Alder Lane, Watery Lane and vice versa.

All business will be open as normal during these works.

Pedestrian access will be maintained at all times during the works.