Warrington West Station

Latest News

The Contractor had a very productive few days on site during the Xmas period, whilst there was a rail closure on the line. You will notice big changes on site, following the installation of the lift shafts, footbridge and staircases. Scaffolding has also been erected so that the cladding can be installed onto the lift shafts. Work will now continue on the platforms with completion of the retaining walls, cladding and installation of the various cabling and equipment required.  The requirement for overnight works should now be less frequent.

Warrington west station

 

Our Contractor will be progressing as much work as possible during the day time to reduce disturbance to local residents at night, however there are unfortunately some activities that can only be carried out during the night time  under Network Rail’s Safety Policy. 

Please see our latest update [docx] and logistics plan [pdf] which explains the activities that will be carried out the next three weeks. 

Night time noise was conditioned as part of the planning process and there are a number of control measures our contractor must adopt to minimise noise and disruption.


We apologise for any disruption caused to date and for any future disruption.

Newsletters

Key dates

  • Executive approval/ Contract award - November 2017
  • Start Enabling Works/ Site set up - December 2017
  • Commence construction - January 2018
  • Road closure:
    • Sycamore Lane - 29 May 18 - 26 April 2019
  • Opening of temporary footpath from Skelton’s Bridge alongside the apartments to Oklahoma Boulevard – March 2018
  • Construction completion - summer 2019
  • Station opening - as soon as possible following construction

Planning Approval

The scheme was heard at Planning Committee on 19 July 2017 where the planning application was unanimously approved.

Consultation events

Between November 2018 and January 2019 we consulted residents living on the streets closest to the new station about proposals for parking restrictions on their streets. We are now reviewing the responses to that consultation.

When will the station open?

We're anticipating works to be completed in summer 2019 with the station being open to the public following approval from the Office of Road and Rail.

If you require any further information, please contact us via email to wws@warrington.gov.uk

Project partly funded by:
Local Growth Deal - £ 6.53m
New Station Fund 2  - £ 4.23m