Scheme Overview

Coronavirus update

Following various updates and guidance provided by government regarding coronavirus and the construction industry, work will recommence from 18 May 2020.

Scheme

The results from our consultation undertaken in October 2018 identified clear support for the introduction of traffic calming measures to Smith Drive, Hallfields Road, Withers Avenue and Hallows Avenue. 

The plans of the scheme can be downloaded [pdf].  Works have been delayed due to the coronavirus pandemic. Works will resume from 18 May 2020.

These works will be monitored in line with any further amendments/guidance specified by Government or the Construction Leadership Council relating to the Covid 19 pandemic.

If you have any comments or queries, then please contact us via email at [email protected].

Scheme Detail
Project phases

Installation of speed cushions partially completed.

Smith Drive

The duration of these works will be four weeks, with work recommencing after the coronavirus pandemic from Monday 18 May. Anticipated completion - 15 June 2020.

The following works will be undertaken during road closure:

  • Smith Drive Junction with Lyndale Avenue (Partially completed)
  • Smith Drive Junction with Roscoe Avenue (Partially completed)
  • Smith Drive Junction Orford (to complete central island)
  • Construction of new speed tables

Withers Avenue junction with Hallsall Avenue

The duration of these works will be two weeks. Commencing 8 June - anticipated completion 23 June.

All works will be undertaken during road closure.

Hallows Avenue

The duration of these works will be three weeks. Commencing 24 June - anticipated completion 8 July.

All works will be undertaken during road closure.

Hallfields Road

The duration of these works will be two weeks. Commencing 9 July - anticipated completion 24 July.

All works will be undertaken during temporary two/three way traffic signals.