Scheme Overview
Roadworks sign

-

09:30 - 15:30
Scheme Detail

Traffic signal upgrades will be carried out at various locations across the borough from February to June 2024 as indicated below.

Whilst the permanent signals are out of commission a temporary set of signals, including facilities for pedestrians crossing, will be provided at each location.

Warrington Road, Penketh Nr. Greystone Road - The scheme will commence on Monday 20 May for approx. 3 weeks. (updated 04/04/24) 

Knutsford Road, Latchford Nr. Grammar School Road - The scheme will commence on Monday 8 April for approx. 3 weeks. (updated 04/04/24) 

Thelwall Lane, Latchford Nr. Lockett Street - The scheme will commence on Monday 29 April for approx. 3 weeks. (updated 04/04/24) 

Warrington Road, Culcheth Nr. Newchurch Lane - The scheme will commence on Monday 10 June for approx. 3 weeks. (date revised 29/02/24)

Completed

  • Chapel Lane, Burtonwood
  • Warrington Road, Penketh Nr. Tavistock Road
  • Warrington Road, Penketh Nr. Clifford Road

If you require any more information, then please contact  [email protected]